Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$18,597.67listed total
Nonerank by 2025 new single-family permits

Not included: Tega Cay SC (inside city): water tap 1,150 and water capacity 900 (3/4 inch domestic), sewer capacity 4 inch 2,250, water + wastewater development impact fees for a 0.75 inch meter 1,107 + 764 = 2,211 (the Development Services sheet prints the same 2,211 total as 1,002 + 1,209), and the city impact fees for a single family unit (parks 5,019, police 754, fire 1,820, public works 331 = 7,924), plus the residential building permit 0.80% of the computed 380,268 valuation (3,042.14), 25% plan review, zoning compliance permit 350 and land disturbance permit 350, all effective July 1 2026. NOT included: administrative review 100, stormwater plan review 300, trade permits, York County and school fees, 2% bank fee, deposit 100, service activation 50. 2026-11-09 lane B.

Water/sewer provider:

LinePrinted ratePrototypeReceipt
Domestic water tap fee, 3/4 inch meter
water
$1,150
3/4 inch domestic meter
$1,150Printed
Effective 2026-07-01
Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Domestic Tap Fee
fetched 2026-11-09, sha256 054a31bdce1b
Domestic water capacity fee, 3/4 inch meter
water
$900
3/4 inch domestic meter
$900Printed
Effective 2026-07-01
Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Domestic Capacity
fetched 2026-11-09, sha256 054a31bdce1b
Sewer capacity fee, 4 inch
sewer
$2,250 (4 inch); $3,000 (6 inch)
4 inch residential sewer connection
$2,250Printed
Effective 2026-07-01
Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Sewer Capacity Fees
fetched 2026-11-09, sha256 054a31bdce1b
Water development impact fee, 0.75 inch meter
water
$1,107 (Utility sheet); total water + wastewater $2,211
0.75 inch meter
$1,107Printed (utility sheet split)
Effective 2026-07-01
Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Water & Sewer Development Impact Fees
fetched 2026-11-09, sha256 054a31bdce1b
Wastewater development impact fee, 0.75 inch meter
sewer
$764 (Utility sheet); total water + wastewater $2,211
0.75 inch meter
$764Printed (utility sheet split)
Effective 2026-07-01
Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Water & Sewer Development Impact Fees
fetched 2026-11-09, sha256 054a31bdce1b
Parks & Recreation impact fee, single family unit
parks
$5,019 per housing unit
per single family unit
$5,019Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees
fetched 2026-11-09, sha256 62db72598fb6
Police impact fee, single family unit
police
$754 per housing unit
per single family unit
$754Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees
fetched 2026-11-09, sha256 62db72598fb6
Fire impact fee, single family unit
fire
$1,820 per housing unit
per single family unit
$1,820Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees
fetched 2026-11-09, sha256 62db72598fb6
Public Works impact fee, single family unit
general
$331 per housing unit
per single family unit
$331Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees
fetched 2026-11-09, sha256 62db72598fb6
Building permit, residential
permit · computed
$15,000 and over project total cost valuation: 0.80% of the project total cost valuation
valuation $380,268 (ICC BVD convention; the city may compare the owner cost to ICC data)
$3,042.140.008 x 380,268 = 3042.14
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Building, Building Permit (Residential)
fetched 2026-11-09, sha256 62db72598fb6
Residential plan review
permit · computed
25% of the Building Permit Fee
25% of the building permit fee
$760.530.25 x 3042.14 = 760.53
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Building, Residential Plan Review
fetched 2026-11-09, sha256 62db72598fb6
Zoning compliance permit, residential new construction
permit
$350
requires land disturbance and building permit
$350Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Zoning & Land Disturbance
fetched 2026-11-09, sha256 62db72598fb6
Land disturbance permit, residential new construction
permit
$350
per residential new construction
$350Printed
Effective 2026-07-01
Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Zoning & Land Disturbance
fetched 2026-11-09, sha256 62db72598fb6
Total listed$18,597.67

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.