Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Tega Cay SC (inside city): water tap 1,150 and water capacity 900 (3/4 inch domestic), sewer capacity 4 inch 2,250, water + wastewater development impact fees for a 0.75 inch meter 1,107 + 764 = 2,211 (the Development Services sheet prints the same 2,211 total as 1,002 + 1,209), and the city impact fees for a single family unit (parks 5,019, police 754, fire 1,820, public works 331 = 7,924), plus the residential building permit 0.80% of the computed 380,268 valuation (3,042.14), 25% plan review, zoning compliance permit 350 and land disturbance permit 350, all effective July 1 2026. NOT included: administrative review 100, stormwater plan review 300, trade permits, York County and school fees, 2% bank fee, deposit 100, service activation 50. 2026-11-09 lane B.
Water/sewer provider:
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Domestic water tap fee, 3/4 inch meter water | $1,150 3/4 inch domestic meter | $1,150 | Printed Effective 2026-07-01 Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Domestic Tap Fee fetched 2026-11-09, sha256 054a31bdce1b |
| Domestic water capacity fee, 3/4 inch meter water | $900 3/4 inch domestic meter | $900 | Printed Effective 2026-07-01 Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Domestic Capacity fetched 2026-11-09, sha256 054a31bdce1b |
| Sewer capacity fee, 4 inch sewer | $2,250 (4 inch); $3,000 (6 inch) 4 inch residential sewer connection | $2,250 | Printed Effective 2026-07-01 Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Sewer Capacity Fees fetched 2026-11-09, sha256 054a31bdce1b |
| Water development impact fee, 0.75 inch meter water | $1,107 (Utility sheet); total water + wastewater $2,211 0.75 inch meter | $1,107 | Printed (utility sheet split) Effective 2026-07-01 Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Water & Sewer Development Impact Fees fetched 2026-11-09, sha256 054a31bdce1b |
| Wastewater development impact fee, 0.75 inch meter sewer | $764 (Utility sheet); total water + wastewater $2,211 0.75 inch meter | $764 | Printed (utility sheet split) Effective 2026-07-01 Source · Tega Cay Utility Department Fee Schedule (effective July 1 2026), Water & Sewer Development Impact Fees fetched 2026-11-09, sha256 054a31bdce1b |
| Parks & Recreation impact fee, single family unit parks | $5,019 per housing unit per single family unit | $5,019 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees fetched 2026-11-09, sha256 62db72598fb6 |
| Police impact fee, single family unit police | $754 per housing unit per single family unit | $754 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees fetched 2026-11-09, sha256 62db72598fb6 |
| Fire impact fee, single family unit fire | $1,820 per housing unit per single family unit | $1,820 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees fetched 2026-11-09, sha256 62db72598fb6 |
| Public Works impact fee, single family unit general | $331 per housing unit per single family unit | $331 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Residential Impact Fees fetched 2026-11-09, sha256 62db72598fb6 |
| Building permit, residential permit · computed | $15,000 and over project total cost valuation: 0.80% of the project total cost valuation valuation $380,268 (ICC BVD convention; the city may compare the owner cost to ICC data) | $3,042.14 | 0.008 x 380,268 = 3042.14 Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Building, Building Permit (Residential) fetched 2026-11-09, sha256 62db72598fb6 |
| Residential plan review permit · computed | 25% of the Building Permit Fee 25% of the building permit fee | $760.53 | 0.25 x 3042.14 = 760.53 Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Building, Residential Plan Review fetched 2026-11-09, sha256 62db72598fb6 |
| Zoning compliance permit, residential new construction permit | $350 requires land disturbance and building permit | $350 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Zoning & Land Disturbance fetched 2026-11-09, sha256 62db72598fb6 |
| Land disturbance permit, residential new construction permit | $350 per residential new construction | $350 | Printed Effective 2026-07-01 Source · Tega Cay Development Services & Impact Fee Schedule (effective July 1 2026), Zoning & Land Disturbance fetched 2026-11-09, sha256 62db72598fb6 |
| Total listed | $18,597.67 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199
Delivered as a web page and PDF within 1 business day.
Watch this jurisdiction
Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.