Gresham, OR
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Full set of posted water, sewer, impact, tap and building permit lines (plumbing, mechanical and electrical permits and other items listed below are not included). Included: Gresham transportation, parks, stormwater, wastewater and water SDCs (effective July 1 2026 per master fee schedule), 3/4-inch water meter and single service installation, structural permit and 65% plan review on a computed $380,268 valuation. Parks and stormwater use the highest printed area (Springwater); city limits are lower ($5,317 and $1,524). Stormwater assumes one 2,500 sq ft drainage unit. Missing: plumbing, mechanical and electrical permits, Oregon state surcharge on permit fees, fire sprinkler permit, Gresham-Barlow school and Metro construction excise taxes. Searched 2026-11-09.
Water/sewer provider: City of Gresham (water, wastewater, stormwater)
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Transportation SDC, Housing Detached (Resolution 3702, eff. July 1 2026) transport | $10,428.00 per detached home | $10,428 | Total rate (improvement 9,426.33 + reimbursement 1,001.67); table read visually and transcribed Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.60 fetched 2026-11-09, sha256 30ded87f3d3c |
| Parks SDC per dwelling unit, highest printed area (Springwater plan district; Pleasant Valley $7,199; current city limits $5,317) parks · computed | $9,232.00 per dwelling unit by area | $9,232 | Highest printed area shown; range $5,317 to $9,232 Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.58 fetched 2026-11-09, sha256 30ded87f3d3c |
| Stormwater SDC per Drainage Residential Unit, highest printed area (Springwater $2,639; Pleasant Valley $2,555; city limits $1,524) stormwater · computed | $2,639.00 per 2,500 sq ft impervious area | $2,639 | Highest printed area shown; one drainage residential unit assumed (2,500 sq ft impervious); range $1,524 to $2,639 Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.59 fetched 2026-11-09, sha256 30ded87f3d3c |
| Wastewater SDC, 3/4-inch meter (improvement 5,335.17 + reimbursement 2,656.83) sewer | $7,992.00 per 3/4" meter | $7,992 | Total printed Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.61 fetched 2026-11-09, sha256 30ded87f3d3c |
| Water SDC, 3/4-inch meter (improvement 5,489.77 + reimbursement 3,877.23) water | $9,367.00 per 3/4" meter | $9,367 | Total printed Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.62 fetched 2026-11-09, sha256 30ded87f3d3c |
| Water meter 3/4-inch, including installation tap | $400.00 each | $400 | Printed Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, water service installation fetched 2026-11-09, sha256 30ded87f3d3c |
| Single water service installation incl. tapping main and 1-inch service, up to 18 ft tap | $2,950.00 each | $2,950 | Printed; extra length $27 per foot beyond 18 ft not included Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, water service installation fetched 2026-11-09, sha256 30ded87f3d3c |
| Building permit, ORSC valuation scale, $100,001 to $500,000 tier, valuation $380,268 permit · computed | $1,022.00 first $100,000 + $7.91 per additional $1,000 or fraction valuation | $3,244.71 | $1,022.00 + 281 x $7.91 = $3,244.71 on computed valuation $380,268 (ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400) Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.35-36 fetched 2026-11-09, sha256 30ded87f3d3c |
| Plan review fee, 65% of building permit fee permit · computed | 65% of permit fee | $2,109.06 | 0.65 x $3,244.71 = $2,109.06 Effective 2026-07-01 Source · City of Gresham Master Fee Schedule effective 7/01/2026, p.38 fetched 2026-11-09, sha256 30ded87f3d3c |
| Total listed | $48,361.77 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199