Dublin, OH

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

Impact fees verifiedno total: permit and tap fees not posted
Nonerank by 2025 new single-family permits

Impact fees verified. Not a full total. Impact fees verified: water capacity charge 3/4-inch tap $1,890, sewer capacity charge $2,210 plus Columbus sewer capacity $3,044 and Dublin inspection fee $175 (total due to the City of Dublin for sewer $5,429), from the City of Dublin 2025 Water/Sewer Fee Schedule A. Not included: City of Columbus water capacity charges (billed by Columbus, not posted here), building permit fee (the 2023 residential fee sheet lists only plumbing $70 first fixture + $20 each additional, sanitary sewer inspection $150 and other service fees, no new-house permit rate), tap installation costs. This page never shows a total. Searched 2026-11-09 (lane A).

Water/sewer provider: City of Dublin

LinePrinted ratePrototypeReceipt
Water capacity charge, domestic, 3/4-inch tap (collected by Dublin; excludes Columbus water capacity)
impact
$1,890.00
per tap
$1,890Printed
Effective 2025-01-01
Source · City of Dublin OH 2025 Water/Sewer Fee Schedule A (capacity charges collected by the City of Dublin), 3/4-inch tap, Water Capacity Charges
fetched 2026-11-09, sha256 c748204d10e7
Dublin sewer capacity charge, 3/4-inch tap
impact
$2,210.00
per tap
$2,210Printed
Effective 2025-01-01
Source · City of Dublin OH 2025 Water/Sewer Fee Schedule A (capacity charges collected by the City of Dublin), 3/4-inch tap, Sewer Capacity Charges
fetched 2026-11-09, sha256 c748204d10e7
Columbus sewer capacity charge collected by Dublin, 3/4-inch tap
impact
$3,044.00
per tap
$3,044Printed
Effective 2025-01-01
Source · City of Dublin OH 2025 Water/Sewer Fee Schedule A (capacity charges collected by the City of Dublin), 3/4-inch tap, Sewer Capacity Charges
fetched 2026-11-09, sha256 c748204d10e7
Dublin sewer inspection fee, 3/4-inch tap
sewer
$175.00
per tap
$175Printed
Effective 2025-01-01
Source · City of Dublin OH 2025 Water/Sewer Fee Schedule A (capacity charges collected by the City of Dublin), 3/4-inch tap, Sewer Capacity Charges
fetched 2026-11-09, sha256 c748204d10e7

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199