High Point, NC
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: High Point NC: water SDF 1,988 and sewer SDF 1,990 (5/8 x 3/4 inch meter), water tap 1,610 plus meter 170, sewer 4 inch tap 2,080, new residential structure permit at ICC value x 0.005 on computed valuation $380,268 (includes electrical, mechanical, plumbing and zoning inspections), NC Homeowner Recovery Fee $10, all from the City of High Point Comprehensive Fee Schedule FY 26-27 (July 1 2026). The older SDF page also lists 3,575.84 total for the prior year. High Point has no road/parks impact fee. NOT included: frontage fees ($10 per linear foot sewer, $7 water, where applicable), irrigation meter, outside-city rates, Guilford/Randolph county fees. 2026-11-09 lane B.
Water/sewer provider:
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Water system development fee, 5/8 x 3/4 inch meter water | $1,988.00 per connection | $1,988 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Water Resources, System Development Fees fetched 2026-11-09, sha256 f1ea97c28db3 |
| Sewer system development fee, 5/8 x 3/4 inch meter sewer | $1,990.00 per connection | $1,990 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Water Resources, System Development Fees fetched 2026-11-09, sha256 f1ea97c28db3 |
| Water tap only, 5/8 inch (no meter) water | $1,610.00 per tap | $1,610 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Water Resources, Tap/Meter Fee Structure - Residential fetched 2026-11-09, sha256 f1ea97c28db3 |
| Water meter, 5/8 inch water | $170.00 per meter | $170 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Water Resources, Tap/Meter Fee Structure - Residential fetched 2026-11-09, sha256 f1ea97c28db3 |
| Sewer service line tap, 4 inch (with clean-out) sewer | $2,080.00 per tap | $2,080 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Water Resources, Sewer service line with clean-out fetched 2026-11-09, sha256 f1ea97c28db3 |
| Residential new structure permit (includes electrical, mechanical, plumbing and zoning inspections) permit · computed | ICC table value x 0.005 (building area over 1,300 sq ft) valuation $380,268 (ICC 175.92 x 2,000 + 71.07 x 400) | $1,901.34 | 380,268 x 0.005 = 1,901.34 Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Development, Module 4 Residential Construction Permit fetched 2026-11-09, sha256 f1ea97c28db3 |
| NC Homeowner Recovery Fee permit | $10.00 mandatory state fee per single-family construction permit | $10 | Printed Effective 2026-07-01 Source · City of High Point Comprehensive Fee Schedule FY 26-27, Development, Module 4 Residential Construction Permit fetched 2026-11-09, sha256 f1ea97c28db3 |
| Total listed | $9,749.34 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199
Delivered as a web page and PDF within 1 business day.
Watch this jurisdiction
Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.