Rochester, MN

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$27,015.09listed total
Nonerank by 2025 new single-family permits

Not included: Included: sewer and water connection fee (maximum per lot, single-family lot one-half acre or less), wastewater plant investment fee, 4-inch sewer tap, valuation-based building permit with 65% plan review (2026 Master Fee Schedule, city-posted PDF; fee columns are 2026 then 2025). Valuation permit uses the project convention $380,268 (computed). The connection fee is frontage-based with a per-lot maximum; the maximum is shown because the per-foot amount depends on lot frontage. Not included: RPU (Rochester Public Utilities) water meter/service charges, per-acre water and sewer availability charges (per developable acre), electrical/plumbing/mechanical permits (separate schedule lines not loaded), parks and other fees not posted. A 2027 schedule is posted but not yet effective. Searched 2026-11-09 (lane A).

Water/sewer provider: City of Rochester

LinePrinted ratePrototypeReceipt
Sewer and water connection fee (combined water and sewer service), developed single-family lot one-half acre or less (maximum per lot)
water
$19,751.23 (parcels under a recorded ENR agreement: $21,234.45)
per lot
$19,751.23Printed maximum per lot; 7,000 sq ft lot is under one-half acre
Effective 2026-01-01
Source · 2026 Master Fee Schedule (adopted Dec 1 2025, amended Aug 3 2026), Utilities
fetched 2026-11-09, sha256 c5c5a2e289be
Wastewater plant investment fee (PIF), residential
sewer
$4,350.00
per residential unit
$4,350Printed
Effective 2026-01-01
Source · 2026 Master Fee Schedule (adopted Dec 1 2025, amended Aug 3 2026), Wastewater Fee Residential PIF
fetched 2026-11-09, sha256 c5c5a2e289be
Sewer tap, 4-inch pipe
sewer
$219.41
per tap
$219.41Printed
Effective 2026-01-01
Source · 2026 Master Fee Schedule (adopted Dec 1 2025, amended Aug 3 2026), Sewer Taps
fetched 2026-11-09, sha256 c5c5a2e289be
Building permit, total valuation $100,001 to $500,000 (valuation $380,268 computed)
permit · computed
$649.50 first $100,000 + $3.50 per each additional $1,000
valuation tier
$1,633649.50 + 3.50 x 281 (each $1,000 or fraction of 280,268) = 1,633.00; valuation 380,268 = ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400
Effective 2026-01-01
Source · 2026 Master Fee Schedule (adopted Dec 1 2025, amended Aug 3 2026), Building Permit Fees
fetched 2026-11-09, sha256 c5c5a2e289be
Building plan review, IRC structures (percent of building permit fee)
permit · computed
65%
percent of permit fee
$1,061.4565% x 1,633.00 = 1,061.45
Effective 2026-01-01
Source · 2026 Master Fee Schedule (adopted Dec 1 2025, amended Aug 3 2026), Building Plan Review Fees
fetched 2026-11-09, sha256 c5c5a2e289be
Total listed$27,015.09

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.