Prior Lake, MN
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Included (the city prints an all-inclusive estimate for a new home): Metropolitan Council SAC $2,485, sewer and water connection fee $2,394, water tower fee $1,200, 5/8-inch water meter $770, pressure reducer $190, sewer and water permit fee $55.50, plumbing $155.50 and mechanical $155.50 permits, and the valuation-based permit $3,083.40, plan check 65% = $2,004.21 and state surcharge $190.13 computed on the ICC valuation $380,268 using the city printed examples ($300,000 and $400,000 values) to get the $6.75 per $1,000 scale (City of Prior Lake Fees Associated with New Home Permits 2026). Not included: fireplace permit $74, builder deposit $2,500 (refundable), other 2026 fee schedule items. Searched 2026-11-09 (lane A).
Water/sewer provider: City of Prior Lake
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Metropolitan Council SAC charge sewer | $2,485.00 per SAC unit | $2,485 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Sewer & water connection fee sewer | $2,394.00 per new home | $2,394 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Water tower fee water | $1,200.00 per new home | $1,200 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Water meter 5/8-inch water | $770.00 per meter | $770 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Pressure reducer 5/8-inch water | $190.00 per new home | $190 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Sewer & water permit fee water | $55.50 per new home | $55.50 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Permit fee, new home (valuation based) permit · computed | $2,536.65 at $300,000 value; $3,211.65 at $400,000 value valuation 380,268 (ICC convention) | $3,083.40 | 2,536.65 + 81 x 6.75 = 3,083.40; valuation 380,268 = 175.92 x 2,000 + 71.07 x 400 (ICC); permit scale taken from the city printed examples: $2,536.65 at $300,000 and $3,211.65 at $400,000, i.e. $6.75 per additional $1,000 or fraction Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Plan check fee permit · computed | 65% of the permit fee 65% of 3,083.40 | $2,004.21 | 0.65 x 3,083.40 = 2,004.21 Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| State surcharge permit · computed | $150.00 at $300,000 value (0.0005 x valuation) valuation 380,268 | $190.13 | 0.0005 x 380,268 = 190.13 Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Plumbing permit fee permit | $155.50 per new home | $155.50 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Mechanical permit fee permit | $155.50 per new home | $155.50 | Printed Effective 2026-01-01 Source · City of Prior Lake Fees Associated with New Home Permits 2026 (printed estimate for a new home) fetched 2026-11-09, sha256 5275d8b9fdf1 |
| Total listed | $12,683.24 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199
Delivered as a web page and PDF within 1 business day.