Lino Lakes, MN
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Included: city trunk sewer and water charges, city sewer and water availability charges (1 SAC unit), sewer and water connection inspections, valuation building permit with 65% plan review, new-construction HVAC and erosion control inspection fees (2026 Fee Schedule ordinance; the PDF is a redline, the struck-through 2025 amounts were identified visually and the new amounts used). Valuation uses the project convention $380,268. Not included: Metropolitan Council SAC (printed only as "Per Met Council", no amount), plumbing at $11 per fixture (fixture count not known), water meter + MXU ("City cost plus $50", cost not posted), special connection fees for named street projects, grading permit $160, electrical. Searched 2026-11-09 (lane A).
Water/sewer provider: City of Lino Lakes
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| City trunk sanitary sewer charge, residential sewer | $1,855/unit per dwelling unit | $1,855 | Printed (2025 amount $1,801 struck) Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)1 Trunk charge fetched 2026-11-09, sha256 c4c841f549c9 |
| City trunk water charge, residential water | $2,666/unit per dwelling unit | $2,666 | Printed (2025 amount $2,588 struck) Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)1 Trunk charge fetched 2026-11-09, sha256 c4c841f549c9 |
| City sewer availability charge (CSAC) sewer | $1,737/SAC unit per SAC unit | $1,737 | Printed, residential 1 SAC unit per dwelling (2025 amount $1,686 struck) Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)2 Availability charge fetched 2026-11-09, sha256 c4c841f549c9 |
| City water availability charge (CWAC) water | $1,677/SAC unit per SAC unit | $1,677 | Printed, residential 1 SAC unit per dwelling (2025 amount $1,628 struck) Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)2 Availability charge fetched 2026-11-09, sha256 c4c841f549c9 |
| Sewer connection inspection fee sewer | $200 per connection | $200 | Printed Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees fetched 2026-11-09, sha256 c4c841f549c9 |
| Water connection inspection fee water | $250 per connection | $250 | Printed Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees fetched 2026-11-09, sha256 c4c841f549c9 |
| Building permit, valuation tier $100,001 to $500,000 (valuation $380,268 computed) permit · computed | $993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof valuation tier | $2,567.35 | 993.75 + 5.60 x 281 (each $1,000 or fraction of 280,268) = 2,567.35; valuation 380,268 = ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400 Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (7) Building Fee Table fetched 2026-11-09, sha256 c4c841f549c9 |
| Plan review fee permit · computed | 65% of the building permit fee percent of permit fee | $1,668.78 | 65% x 2,567.35 = 1,668.78 Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees fetched 2026-11-09, sha256 c4c841f549c9 |
| Mechanical (HVAC) fee: new construction residential permit | $158 (does not include fireplaces) flat | $158 | Printed Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees fetched 2026-11-09, sha256 c4c841f549c9 |
| Erosion control inspection fee, single family permit | $160 per lot | $160 | Printed Effective 2026-01-01 Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees fetched 2026-11-09, sha256 c4c841f549c9 |
| Total listed | $12,939.13 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199