Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$12,939.13listed total
Nonerank by 2025 new single-family permits

Not included: Included: city trunk sewer and water charges, city sewer and water availability charges (1 SAC unit), sewer and water connection inspections, valuation building permit with 65% plan review, new-construction HVAC and erosion control inspection fees (2026 Fee Schedule ordinance; the PDF is a redline, the struck-through 2025 amounts were identified visually and the new amounts used). Valuation uses the project convention $380,268. Not included: Metropolitan Council SAC (printed only as "Per Met Council", no amount), plumbing at $11 per fixture (fixture count not known), water meter + MXU ("City cost plus $50", cost not posted), special connection fees for named street projects, grading permit $160, electrical. Searched 2026-11-09 (lane A).

Water/sewer provider: City of Lino Lakes

LinePrinted ratePrototypeReceipt
City trunk sanitary sewer charge, residential
sewer
$1,855/unit
per dwelling unit
$1,855Printed (2025 amount $1,801 struck)
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)1 Trunk charge
fetched 2026-11-09, sha256 c4c841f549c9
City trunk water charge, residential
water
$2,666/unit
per dwelling unit
$2,666Printed (2025 amount $2,588 struck)
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)1 Trunk charge
fetched 2026-11-09, sha256 c4c841f549c9
City sewer availability charge (CSAC)
sewer
$1,737/SAC unit
per SAC unit
$1,737Printed, residential 1 SAC unit per dwelling (2025 amount $1,686 struck)
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)2 Availability charge
fetched 2026-11-09, sha256 c4c841f549c9
City water availability charge (CWAC)
water
$1,677/SAC unit
per SAC unit
$1,677Printed, residential 1 SAC unit per dwelling (2025 amount $1,628 struck)
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (e)2 Availability charge
fetched 2026-11-09, sha256 c4c841f549c9
Sewer connection inspection fee
sewer
$200
per connection
$200Printed
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees
fetched 2026-11-09, sha256 c4c841f549c9
Water connection inspection fee
water
$250
per connection
$250Printed
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees
fetched 2026-11-09, sha256 c4c841f549c9
Building permit, valuation tier $100,001 to $500,000 (valuation $380,268 computed)
permit · computed
$993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof
valuation tier
$2,567.35993.75 + 5.60 x 281 (each $1,000 or fraction of 280,268) = 2,567.35; valuation 380,268 = ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (7) Building Fee Table
fetched 2026-11-09, sha256 c4c841f549c9
Plan review fee
permit · computed
65% of the building permit fee
percent of permit fee
$1,668.7865% x 2,567.35 = 1,668.78
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees
fetched 2026-11-09, sha256 c4c841f549c9
Mechanical (HVAC) fee: new construction residential
permit
$158 (does not include fireplaces)
flat
$158Printed
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees
fetched 2026-11-09, sha256 c4c841f549c9
Erosion control inspection fee, single family
permit
$160
per lot
$160Printed
Effective 2026-01-01
Source · Lino Lakes Fee Schedule ordinance (effective January 1, 2026; new amounts after struck-through 2025 amounts), (c) Other inspections and fees
fetched 2026-11-09, sha256 c4c841f549c9
Total listed$12,939.13

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199