Padstake
Menu

Elk River, MN

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$21,240.99listed total
Nonerank by 2025 new single-family permits

Not included: Included: SAC $6,426, water access charge $3,990 ($3,600 builder connection + $390 developer availability), sewer and water hookup permit $100, residential park dedication fee (highest density tier $5,945.38 shown as headline; low density $3,065.73, medium $4,207.25), building permit $2,781.50 on the computed ICC valuation $380,268, plan review 65% = $1,807.98 and state surcharge $190.13 (City of Elk River 2026 Master Fee Schedule; the city prints no new-house valuation rate). Not included: water meter fee (handled by Elk River Municipal Utilities, no price posted in this schedule), plumbing/mechanical permits, stormwater utility fee, trunk or area charges (not printed in this schedule). Searched 2026-11-09 (lane A).

Water/sewer provider: City of Elk River

LinePrinted ratePrototypeReceipt
Sewer Availability Charge (SAC)
sewer
$6,426 per unit
1 unit
$6,426Printed
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A)
fetched 2026-11-09, sha256 cf81ede930c8
Water Access Charge = water connection charge (builder) $3,600 + water availability charge (developer) $390
water · computed
$3,990.00
per plumbing unit
$3,9903,600 + 390 = 3,990
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A)
fetched 2026-11-09, sha256 cf81ede930c8
Sewer and water hookup permit, residential
sewer
$100 residential
per permit
$100Printed
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A), Sewer & Water Hookup/Repair Permit
fetched 2026-11-09, sha256 cf81ede930c8
Park dedication fee, residential
impact · computed
$5,945.38/dwelling unit high density (low density $3,065.73; medium density $4,207.25)
per dwelling unit
$5,945.38Highest printed density shown as headline; low density $3,065.73
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A), Park Dedication Fee
fetched 2026-11-09, sha256 cf81ede930c8
Building permit, new house (valuation based)
permit · computed
$1,095.50 for the first $100,000 + $6 per additional $1,000 or fraction, to $500,000
valuation 380,268 (ICC convention)
$2,781.501,095.50 + 281 x 6 = 2,781.50; valuation 380,268 = 175.92 x 2,000 + 71.07 x 400
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A), Building Permit
fetched 2026-11-09, sha256 cf81ede930c8
Plan review fee
permit · computed
65% of the permit fee
65% of 2,781.50
$1,807.980.65 x 2,781.50 = 1,807.98
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A), Plan Review Fee
fetched 2026-11-09, sha256 cf81ede930c8
State of Minnesota surcharge
permit · computed
0.0005 times the valuation
valuation 380,268
$190.130.0005 x 380,268 = 190.13
Effective 2026-01-01
Source · City of Elk River 2026 Master Fee Schedule (Exhibit A), State of Minnesota Surcharge
fetched 2026-11-09, sha256 cf81ede930c8
Total listed$21,240.99

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.