Hampshire village, IL
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Included: village water and sewer connection fees, water meter, school/park/village/fire/library/transportation/cemetery/early-warning impact fees and the six transition fees, plus administration, certificate of occupancy, driveway, energy and water-service inspections (2025 Building Permit Fee Schedule, residential new construction per dwelling unit). Bedroom-based fees use 3 BR single-family (assumed, other bedroom counts shown in each line). Not included: code plan review at $90 per hour and building inspections at $52 per required inspection (hours and inspection counts not posted). The 2025 schedule is the latest posted. Searched 2026-11-09 (lane A).
Water/sewer provider: Village of Hampshire
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Water connection fee, single-family (3 BR SFR) water | $5,200 per dwelling unit | $5,200 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 6 Impact & Connection Fee Schedule (3 BR SFR row) fetched 2026-11-09, sha256 9f43c689ef71 |
| Sewer connection fee, single-family (3 BR SFR) sewer | $6,265 per dwelling unit | $6,265 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 6 Impact & Connection Fee Schedule (3 BR SFR row) fetched 2026-11-09, sha256 9f43c689ef71 |
| Water meter water | $450 per dwelling unit | $450 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Water service line inspection water | $75 per dwelling unit | $75 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| School impact fee, 3 BR single-family impact | $2,851.69 per dwelling unit | $2,851.69 | Printed (bedroom count assumed 3; 2 BR $700.68, 4 BR $4,865.95) Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 6 Impact & Connection Fee Schedule (3 BR SFR row) fetched 2026-11-09, sha256 9f43c689ef71 |
| Park district impact fee, 3 BR single-family parks | $3,768.7 per dwelling unit | $3,768.70 | Printed (bedroom count assumed 3; 2 BR $2662.1, 4 BR $4,893.2) Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 6 Impact & Connection Fee Schedule (3 BR SFR row) fetched 2026-11-09, sha256 9f43c689ef71 |
| Village impact fee, 3 BR single-family impact | $1,507.48 per dwelling unit | $1,507.48 | Printed (bedroom count assumed 3; 2 BR $1,048.84, 4 BR $1,957.28) Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 6 Impact & Connection Fee Schedule (3 BR SFR row) fetched 2026-11-09, sha256 9f43c689ef71 |
| Fire impact fee fire | $600 per dwelling unit | $600 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Library impact fee library | $150 per dwelling unit | $150 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Transportation impact fee transportation | $1,636 per dwelling unit | $1,636 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Cemetery impact fee impact | $80 per dwelling unit | $80 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Early warning impact fee impact | $38.33 per dwelling unit | $38.33 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Village transition fee impact | $887.25 per dwelling unit | $887.25 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| School district transition fee impact | $4,116.19 per dwelling unit | $4,116.19 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Park district transition fee impact | $397.80 per dwelling unit | $397.80 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Fire district transition fee impact | $893.83 per dwelling unit | $893.83 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Library district transition fee impact | $135.25 per dwelling unit | $135.25 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Township transition fee impact | $138.26 per dwelling unit | $138.26 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Administration fee permit | $75 per dwelling unit | $75 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Certificate of occupancy permit | $75 per dwelling unit | $75 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Driveway/sidewalk inspection permit | $150 per dwelling unit | $150 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Energy inspection permit | $75 per dwelling unit | $75 | Printed Effective 2025-01-01 Source · 2025 Building Permit Fee Schedule, page 1 (Residential New Construction per dwelling unit) fetched 2026-11-09, sha256 9f43c689ef71 |
| Total listed | $29,565.78 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199