Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$8,646.60listed total
Nonerank by 2025 new single-family permits

Not included: Oconee County GA (unincorporated): water capacity 2,320 + meter 310 + inspection 165 (5/8 x 3/4 meter), sewer capacity 3,746.60 + county-installed connection 850 + inspection 165 (county sewer is limited to Calls Creek and Rocky Branch areas), building permit 0.47/sq ft x 2,000 sq ft, three residential trade permits at $50 (assumed three), from the FY27 Approved Fee Schedule (FY27 begins July 1 2026). Oconee has no adopted impact fee (study committee only). NOT included: gas permit, soil erosion/land disturbance, water/sewer service deposits, parcels without county sewer would not pay the sewer lines. 2026-11-09 lane B.

Water/sewer provider:

LinePrinted ratePrototypeReceipt
Water availability (capacity) charge, 5/8 x 3/4 inch meter
water
$2,320.00
per connection plus meter fee
$2,320Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Water Resources, Water Services Fee
fetched 2026-11-09, sha256 5ec5878a2b19
Meter installation fee, 5/8 x 3/4 inch meter
water
$310.00
per connection (meter furnished and installed by county)
$310Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Water Resources, Water Services Fee
fetched 2026-11-09, sha256 5ec5878a2b19
Water connection inspection fee
water
$165.00
charged on all water connections
$165Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Water Resources, Water Services Fee
fetched 2026-11-09, sha256 5ec5878a2b19
Residential sewer capacity fee, 1 ERC (Calls Creek WRF and Rocky Branch LAS)
sewer
$3,746.60
per ERC, same at both plants
$3,746.60Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Residential Sewer Capacity Fees
fetched 2026-11-09, sha256 5ec5878a2b19
Sewer connection (county installs)
sewer
$850.00
each connection, only if county performs installation
$850Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Residential Sewer Capacity Fees
fetched 2026-11-09, sha256 5ec5878a2b19
Sewer connection inspection fee
sewer
$165.00
charged on all sewer connections
$165Printed
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Residential Sewer Capacity Fees
fetched 2026-11-09, sha256 5ec5878a2b19
Building permit, single-family dwelling
permit · computed
$0.47 per square foot
per sq ft, 2,000 sq ft heated
$9400.47 x 2,000 = 940.00
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Building Inspection/Code Enforcement, SFD, Duplexes, Multifamily
fetched 2026-11-09, sha256 5ec5878a2b19
Trade permits, residential (plumbing, electrical, HVAC)
permit · computed
$50.00
flat fee per trade, three trades assumed
$1503 x 50.00 = 150.00
Effective 2026-07-01
Source · Oconee County FY27 Approved Fee Schedule, Building Inspection/Code Enforcement, Trade permit - Residential
fetched 2026-11-09, sha256 5ec5878a2b19
Total listed$8,646.60

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.