Ball Ground, GA
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Impact fees verified. Not a full total. IMPACT FEES VERIFIED ONLY, no total. Ball Ground GA: parks 2,000 and road 1,000 impact fees (single-family detached, program effective for permits from Oct 11 2024), sewer capacity charge 6,500 (3/4 inch per REU), water tap 750 + 3/4 inch meter 3,000, and building permit 2,800 (2,000 conditioned x 1.25 + 400 garage x 0.75), from the city fee schedules. The city building page says water capacity fees are due before a permit but no water capacity amount is printed in the stored schedule. NOT included: water capacity fee (not printed), plumbing/electrical/mechanical inspections (150 each), long side service bore 1,000, deposits, Cherokee County fees. 2026-11-09 lane B.
Water/sewer provider:
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Parks and recreation impact fee, single-family detached parks | $2,000 per dwelling (all administrative fees included) per dwelling | $2,000 | Printed Effective 2024-10-11 Source · Fee Schedule Attachment A Impact Fees, Single-Family Detached Housing fetched 2026-11-09, sha256 1bd96d273ffc |
| Road improvements impact fee, single-family detached transportation | $1,000 per dwelling per dwelling | $1,000 | Printed Effective 2024-10-11 Source · Fee Schedule Attachment A Impact Fees, Single-Family Detached Housing fetched 2026-11-09, sha256 1bd96d273ffc |
| Sewer capacity charge, 3/4 inch meter per residential equivalent unit sewer | $6,500.00 per REU, 3/4 inch meter | $6,500 | Printed Effective 2025-01-09 Source · Ball Ground Community Development Fee Schedule (adopted Jan 9 2025), p.9 Sewer Fees fetched 2026-11-09, sha256 cc8dd90ff452 |
| Water line tapping, service and materials water | $750.00 per tap | $750 | Printed Effective 2025-01-09 Source · Ball Ground Community Development Fee Schedule (adopted Jan 9 2025), p.8 Water Service Installation Charges fetched 2026-11-09, sha256 cc8dd90ff452 |
| 3/4 inch meter (Ball Ground furnishes meter, backflow and installation) water | $3,000.00 3/4 inch meter | $3,000 | Printed Effective 2025-01-09 Source · Ball Ground Community Development Fee Schedule (adopted Jan 9 2025), p.8 Water Service Installation Charges fetched 2026-11-09, sha256 cc8dd90ff452 |
| Building permit, new construction permit · computed | (Conditioned space sq ft x $1.25) + (Non-conditioned space sq ft x $0.75); minimum $150 2,000 sq ft conditioned + 400 sq ft garage | $2,800 | 2,000 x 1.25 + 400 x 0.75 = 2800.00 Effective 2025-01-09 Source · Ball Ground Community Development Fee Schedule (adopted Jan 9 2025), p.3 Building Permit Fees fetched 2026-11-09, sha256 cc8dd90ff452 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199
Delivered as a web page and PDF within 1 business day.
Watch this jurisdiction
Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.