Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$58,364.32listed total
Nonerank by 2025 new single-family permits

Not included: Included: valuation permit with building admin (plan review) fee, technology fee and strong motion tax (city own valuation table, $255,832), public facilities fee (1,500-2,500 SF), regional and local sewer connection, low density water connection with meter and construction water, and drainage, traffic, park (highest area) and solid waste impact fees from the July 2026 booklet; area-based fees use the highest printed area and the tables were read visually (transcription appended to the stored text, original kept as .bak-orig). Not included: water pressure zone and reimbursement area fees (parcel specific), sewer special benefit area fees (SSBA3 $706, SSBA4 $7,867), electric backbone impact fee and electric direct installation (Roseville Electric), pooled unit park fee, SPRTA Tier 2, development agreement fees, fire system fees, planning/engineering fees, school district fees, fee deferral fee. Fees by specific plan area; a given parcel may pay less. Searched 2026-11-09.

Water/sewer provider: City of Roseville (water, sewer, electric)

LinePrinted ratePrototypeReceipt
Building permit fee (valuation-based, Appendix C)
permit · computed
$1,219.00 for the first $100,000.00 plus $6.63 for each additional $1000.00, or fraction thereof, to and including $500,000.00
percent of valuation
$2,253.28City valuation $255,832 (Appendix B Table A: R-3 V-B $119.56 x 2,000 sq ft + U V-B $41.78 x 400 sq ft garage); 156 additional $1,000 units x 6.63 + 1,219 = 2,253.28. Uses the city own table, not the Padstake $380,268
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Appendix B and C
fetched 2026-11-09, sha256 9e4532d4bf77
Building admin fee (plan review), non-production single family
permit · computed
Building Permit Fee x .95
multiple of permit fee
$2,140.620.95 x 2,253.28 = 2,140.62
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Building Permits
fetched 2026-11-09, sha256 9e4532d4bf77
Technology fee
permit · computed
x .03
3% of total application and permit fees
$131.823% x (2,253.28 + 2,140.62) = 131.82
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), General
fetched 2026-11-09, sha256 9e4532d4bf77
Strong motion tax (state)
permit · computed
calculated valuation x .00013
multiple of valuation
$33.260.00013 x 255,832 = 33.26
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Building Permits
fetched 2026-11-09, sha256 9e4532d4bf77
Public facilities fee, residential 1,500 to 2,500 SF
general
$6,363.00
per unit, by size (Table 1)
$6,363Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Table 1
fetched 2026-11-09, sha256 9e4532d4bf77
Regional sewer connection fee
sewer
$9,987.00
per sewer/dwelling unit
$9,987Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Regional Sewer Connection Fees
fetched 2026-11-09, sha256 9e4532d4bf77
Local sewer connection fee
sewer
$466.00
per sewer/dwelling unit
$466Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Local Sewer Connection Fee
fetched 2026-11-09, sha256 9e4532d4bf77
Water connection fee, low density residential (Table 2)
water
$13,069.00
per unit
$13,069Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Table 2
fetched 2026-11-09, sha256 9e4532d4bf77
Water meter fee
water
$409.09
per unit
$409.09Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Water Meter Fee
fetched 2026-11-09, sha256 9e4532d4bf77
Water use fee (construction)
water
$75.00
per unit
$75Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Water Use Fee
fetched 2026-11-09, sha256 9e4532d4bf77
Drainage mitigation fee, Dry Creek low density (Miners Ravine)
stormwater
$1,292.12
per new unit
$1,292.12Printed; highest printed zone; Pleasant Grove Creek low density $652.23, other Dry Creek zones $376.24-$791.46
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Appendix L
fetched 2026-11-09, sha256 9e4532d4bf77
Traffic fees total (City TMF + Hwy 65 JPA + SPRTA Regional + City/County), Creekview district
transportation
$12,390.13
per unit
$12,390.13Printed; highest printed benefit district; Infill and Redevelopment $8,397.77
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Appendix M
fetched 2026-11-09, sha256 9e4532d4bf77
Park fees, Westpark (citywide + neighborhood + bike trail + paseo)
parks · computed
$3,221 citywide + $3,908 neighborhood + $1,004 bike trail + $1,211 paseo
per unit
$9,344$3,221 + $3,908 + $1,004 + $1,211 = 9,344; highest combined plan area among those transcribed; in-lieu columns excluded
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Appendix N
fetched 2026-11-09, sha256 9e4532d4bf77
Solid waste impact fee, single family residential
general
$410.00
per unit
$410Printed
Effective 2026-07-01
Source · City of Roseville Residential Development Fees booklet, July 2026-June 2027 (updated July 1, 2026), Table 8
fetched 2026-11-09, sha256 9e4532d4bf77
Total listed$58,364.32

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.