Banning, CA
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Impact fees verified. Not a full total. Impact fees verified only. Included: city police, fire, parks, general facilities, wastewater, traffic, electric and water (3/4-inch meter) development impact fees from Resolution 2026-24, with per-square-foot fees applied to an assumed 2,000 sq ft home (effective March 12, 2026; electric March 26, 2026 or when Ordinance 1616 takes effect). Missing: building permit and plan check fees, water and sewer connection/tap and meter fees, Western Riverside County TUMF and MSHCP fees (separate chapters, excluded from this resolution), school fees. Searched 2026-11-09.
Water/sewer provider: City of Banning (water, wastewater, electric)
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Police facilities impact fee police · computed | $0.90 per sq ft, single family | $1,800 | $0.90 x 2,000 sq ft = 1,800.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Fire protection facilities impact fee fire · computed | $1.26 per sq ft, single family | $2,520 | $1.26 x 2,000 sq ft = 2,520.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Parkland and parks impact fee parks · computed | $3.80 per sq ft, single family | $7,600 | $3.80 x 2,000 sq ft = 7,600.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| General city facilities impact fee general · computed | $1.23 per sq ft, single family | $2,460 | $1.23 x 2,000 sq ft = 2,460.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Wastewater facilities impact fee sewer · computed | $6.39 per sq ft, single family | $12,780 | $6.39 x 2,000 sq ft = 12,780.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Traffic impact fee transportation · computed | $1.23 per sq ft, single family | $2,460 | $1.23 x 2,000 sq ft = 2,460.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Electric impact fee electric · computed | $0.99 per sq ft, single family | $1,980 | $0.99 x 2,000 sq ft = 1,980.00 (2,000 sq ft assumed) Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
| Water facilities impact fee, 3/4-inch meter water | $11,251 per meter size (3/4 inch is the smallest listed) | $11,251 | Printed Effective 2026-03-12 Source · City of Banning Resolution 2026-24, Exhibit A, 2026 Development Impact Fee Schedule (adopted Feb 10, 2026), page 8 fetched 2026-11-09, sha256 5384566bd3bf |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199