Fairhope, AL

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$22,623.34listed total
Nonerank by 2025 new single-family permits

Not included: Fairhope AL: city impact fees single-family $9,237 (Ord. 1817, Dec 2024), water SDC $2,700 + tap $1,000 (1" meter, Ord. 1867, eff. Aug 1 2026), sewer SDC $7,460 (1" meter size, Ord. 1868), building permit 5.00/1000 on computed $380,268 plus plan review, electrical, plumbing, mechanical and sewer tap inspection (Ord. 1844, Oct 2025). NOT included: sewer installation tap (low-pressure tap $750 only if low-pressure service; owner builds gravity service line), security/structured wire $25, temporary electric $25, gas permit (Gas Dept), 3/4-inch meter option for previously approved homes, 2026 amendments for sewer SDC 3/4" ($4,476). Gas permit and trades fees per the 2025 ordinance. 2026-11-09 lane B.

Water/sewer provider:

LinePrinted ratePrototypeReceipt
Fire impact fee, single-family (R-3)
fire
$895
per housing unit
$895Printed
Effective 2024-12-19
Source · Ordinance 1817 (adopted Dec 19 2024), Exhibit A Impact Fee Schedule, Single Family (R-3)
fetched 2026-11-09, sha256 2e71cd34aad8
Police impact fee, single-family (R-3)
police
$1,353
per housing unit
$1,353Printed
Effective 2024-12-19
Source · Ordinance 1817 (adopted Dec 19 2024), Exhibit A Impact Fee Schedule, Single Family (R-3)
fetched 2026-11-09, sha256 2e71cd34aad8
Parks and recreation impact fee, single-family (R-3)
parks
$3,228
per housing unit
$3,228Printed
Effective 2024-12-19
Source · Ordinance 1817 (adopted Dec 19 2024), Exhibit A Impact Fee Schedule, Single Family (R-3)
fetched 2026-11-09, sha256 2e71cd34aad8
Transportation impact fee, single-family (R-3)
transportation
$3,761
per housing unit
$3,761Printed
Effective 2024-12-19
Source · Ordinance 1817 (adopted Dec 19 2024), Exhibit A Impact Fee Schedule, Single Family (R-3)
fetched 2026-11-09, sha256 2e71cd34aad8
Water system development charge, 1" meter
water
$2,700
per connection (1" meter, minimum new residential size)
$2,700Printed
Effective 2026-08-01
Source · Ordinance 1867, Sec. 21-32(c) connection fees, 1-inch residential meter (minimum new size)
fetched 2026-11-09, sha256 eca9e47f487c
Water installation (tap) fee, 1" meter
water
$1,000.00
per connection; charged if no existing service
$1,000Printed
Effective 2026-08-01
Source · Ordinance 1867, Sec. 21-32(c) connection fees, 1-inch residential meter (minimum new size)
fetched 2026-11-09, sha256 eca9e47f487c
Sewer system development charge, 1" water meter size
sewer
$7,460
per connection
$7,460Printed
Effective 2026-08-01
Source · Ordinance 1868, Sec. 21-52(b) SDC wastewater, 1-inch meter
fetched 2026-11-09, sha256 f58e139788d6
Building permit
permit · computed
$5.00 per $1000 of project value (min $100)
valuation $380,268 (ICC 175.92 x 2,000 + 71.07 x 400)
$1,901.345.00 x 380.268 = 1,901.34
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Plan review fee
permit
$75.00
flat
$75Printed
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Electrical permit fee
permit
$75.00
flat, new construction
$75Printed
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Plumbing permit fee
permit
$75.00
flat, new construction
$75Printed
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Mechanical permit fee
permit
$75.00
flat, new construction
$75Printed
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Sewer tap inspection fee
permit
$25.00
flat, residential
$25Printed
Effective 2025-10-13
Source · Ordinance 1844, Sec. 7-7 New Construction Permit Fees, Residential (adopted Oct 13 2025)
fetched 2026-11-09, sha256 12ce3b2f23af
Total listed$22,623.34

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.